Changeovers

Mold Setup Checklist: From Last Good Part to First Good Part

A good setup checklist does two jobs: it stops steps from being skipped, and it makes every setup tech do the job the same way on every shift. Below is a stage-by-stage checklist for injection mold changes. Use it as a starting point and adapt it to your presses, molds and safety procedures.

FR Soft Solution4 min read

How to use this checklist

The checklist follows the stages of a changeover, from staging before the press stops to closing out the job. Each stage has an owner. Record a timestamp when each stage finishes: the gaps between timestamps show where your changeovers wait. That is the idea behind mold setup tracking, and you can do it on paper before you do it in software.

Mold setup stages from scheduled to running, each with an owner and a timestampScheduledScheduler⏱ timestampMaterial readyMaterial handler⏱ timestampMold hungSetup tech⏱ timestampProcess techProcess tech⏱ timestampFirst articleQuality⏱ timestampRunningOperator⏱ timestampEach handoff is one tap. The gaps between timestamps show exactly where a changeover waited.
The stages of a setup, each with an owner. A timestamp at every handoff shows where time is lost.

1. Before the press stops (external work)

Owner: scheduler / setup lead

  • Next job confirmed: press, mold number, material, color, quantity
  • Mold pulled from storage, inspected and staged beside the press
  • Mold maintenance status checked: no open toolroom issues
  • Material loaded in the dryer early enough to reach the required drying time
  • Correct process sheet revision identified and available at the press
  • Setup cart complete: clamps, bolts, hoses, fittings, tools, purge compound
  • Crane or forklift availability confirmed for the planned stop time
  • Quality notified that a first article is coming

2. Shut down and pull the outgoing mold

Owner: setup tech

  • Last good part retained and labeled (useful when the job runs again)
  • Hopper and barrel handled per the material plan (run out, purge or keep)
  • Mold cooling turned off; water blown out of lines if the plant requires it
  • Hot runner, cores and ejector connections disconnected and capped
  • Lockout and crane procedures followed
  • Mold removed; condition noted (damage, flash, water leaks) for the toolroom
  • Platens and locating ring area cleaned

3. Hang the incoming mold

Owner: setup tech

  • Mold height and press opening set for this mold
  • Locating ring seated; mold square to the platens
  • Clamps tightened to specification, evenly
  • Ejector stroke and knock-out pattern set; ejector return confirmed
  • Safety straps or mold lock removed before opening
  • Mold open and close checked slowly; mold protection (low-pressure close) set

4. Connect utilities

Owner: setup tech

  • Water circuits connected per the mold’s water diagram (inlet/outlet, correct temperature unit)
  • Water flow verified on every circuit; no leaks
  • Thermolators set to the process sheet temperatures
  • Hot runner connected; every zone on and at setpoint
  • Cores, slides and valve gates connected and cycled
  • Air blow-offs and any robot or end-of-arm tooling set up

5. Start up the process

Owner: process tech

  • Process sheet revision on the press matches the approved revision
  • Material confirmed dry; correct material and colorant in the hopper
  • Barrel purged to the new material and color
  • Melt temperature measured on an air shot
  • Fill-only shots taken to confirm fill pattern and transfer position
  • Cushion stable; cycle time at the sheet value
  • Process at sheet values; any changes recorded with the reason

6. First article and release

Owner: quality

  • First article taken from every cavity (or per the control plan)
  • Visual check against the defect standard (flash, short, splay, sink, burns)
  • Critical dimensions measured per the control plan
  • First article approved or rejected with a reason; time recorded
  • Press released to production; operator instructions at the press

7. Close out

Owner: setup lead

  • Outgoing mold sent to storage or the toolroom with notes
  • Setup cart restocked for the next changeover
  • Changeover times recorded: last good part, each stage, first good part
  • Delays and their causes recorded (waiting for crane, material, tooling, quality)

Skipped steps and the defects they cause

Most first-shot problems after a changeover trace back to one skipped line on a checklist like this one. When a defect appears right after a setup, check these first:

Skipped stepWhat you seeRead more
Parting line or platens not cleanedFlash on one side, short on the otherInjection molding flash
Old process sheet revision loadedFlash, shorts or sink that "never happened before"Short shots
Material not dried long enoughSilver streaks from the first shotSplay
Hot runner zone left offOne cavity short or frozen gateShort shots
Water circuits swapped or not flowingWarp, sink, longer cycle, stickingCheck the mold water diagram
Hopper not cleaned after the last jobSpecks, color streaks, splaySplay

Adapting the checklist to your plant

  • Per mold family: add the connections, cores and special steps each family needs, and remove what does not apply.
  • Per press size: large presses often need crane booking and rigging steps that small presses do not.
  • Per material: hygroscopic resins need explicit drying checks; color changes need a purge plan.
  • Keep it short: if a line is never skipped and never matters, remove it. A shorter list gets used.
  • Name owners, not departments: "setup tech on shift" is clearer than "maintenance".

Making the checklist stick

A checklist that lives in a binder gets skipped. The ones that work are short, kept at the press, and part of how the work is reported: a step is not done until it is checked off. Review the recorded times every week. The stages that are always slow tell you where to focus, and our guides on reducing changeover time and SMED for injection molding cover what to do about them.

When paper becomes the bottleneck, the same checklist can run on floor tablets in SetupLens, with each step timestamped and the history searchable by press, mold and shift.

Written by

The FR Soft Solution engineering team

FR Soft Solution is a founder-led software company in Louisville, Ohio. Our founder worked on injection molding shop floors before building SetupLens, the mold setup tracking and MES platform we run in production. We write about what we see on molding floors.

FAQ

Questions about this topic

Straight answers on scope, pricing, timelines, and who owns the code. Still unsure? Ask us directly.

Staging before the press stops, shutting down and pulling the old mold, hanging the new mold, connecting water and hot runner, starting the process with the correct sheet revision, first-article approval, and closing out with recorded times and delays.

Tell us what your floor or product needs

Start with a discovery call with the founder. You get a written scope, a timeline, and an estimate, with no obligation.

  • You own 100% of the code
  • Founder-led from day one
  • Louisville, OH and remote